FG SUSPENDS ASEESE PEDESTRIAN BRIDGE CONSTRUCTION INDEFINITELY AFTER 20-HOUR GRIDLOCK

Martha Udom

The Federal Government has indefinitely suspended construction of a pedestrian bridge at Aseese, along the Lagos-Ibadan Expressway, following a traffic gridlock that left motorists stranded for more than 20 hours.

The project, being handled by the Federal Ministry of Works in collaboration with CBC Construction Company, was scheduled to run from Wednesday, November 18, to Sunday, November 22, 2026, to facilitate the installation of the pedestrian bridge.

Under the initial traffic management arrangement, Lagos-bound motorists were to be diverted towards the Lagos carriageway at Aseese before rejoining their normal route at a designated exit opposite Christ Embassy.

However, the diversion triggered severe congestion along the expressway, with traffic reportedly building up from about 2 p.m. on Wednesday and continuing into Thursday morning.

Some commuters spent several hours on journeys that would ordinarily take far less time. A passenger who left Ibadan shortly after 11 a.m. reportedly arrived in Magboro at about 5:30 p.m., while another motorist said he spent eight hours travelling from Mowe to Magboro.

Some commercial motorcyclists reportedly charged as much as ₦6,000 for trips from Mowe to Ibafo.

The Ogun State Traffic Compliance and Enforcement Agency (TRACE) announced the indefinite suspension of the construction work and the associated traffic diversion in a statement issued on Thursday, November 19.

The agency’s spokesperson, Babatunde Akinbiyi, said the decision followed the significant congestion experienced along the corridor from Wednesday into Thursday morning, necessitating a review of the traffic management arrangements.

“Consequently, all motorists are hereby advised that the temporary traffic diversion associated with the pedestrian bridge construction is suspended, pending further directives from the relevant authorities,” Akinbiyi said.

The acting Controller of the Federal Ministry of Works in Ogun State, Richard Adeleye, also confirmed the suspension.

“Yes, it was suspended due to the traffic situation,” Adeleye said.

Meanwhile, President Bola Tinubu’s Special Adviser on Media and Communications, Sunday Dare, criticised the timing of the construction after spending more than five hours in the gridlock while travelling to Ibadan.

Dare questioned why the work was being carried out during busy traffic hours instead of at night when vehicular movement was lighter.

Although the suspension has halted the immediate construction activities, residents and commuters have maintained that the pedestrian bridge is necessary to protect pedestrians who risk their lives crossing the busy expressway.

They, however, want the project to be carried out with better traffic management arrangements to prevent a recurrence of the disruption.

As of Friday morning, November 20, no date had been announced for the resumption of construction.